Lincoln Square Recreation Center

  • Project TypePublic Works
  • Project StatusConstruction Phase
  • Contractor nameS.J. Amoroso Construction Co.
Demolition Zone for Lincoln Square Recreation Center starting October 2026.jpg
 

Demolition Notice

Building demolition is scheduled to begin no earlier than November 4, 2026, Monday through Friday, 8:00 a.m. to 4:00 p.m. See the Demolition Update below for details and contacts.

Demolition Update

Project Scope

The Lincoln Square Recreation Center Project will expand and improve recreation amenities and services to the community pursuing a LEED Gold certification with environmentally friendly construction methods. The Lincoln Square Recreation Center will be the first resiliency center for the City of Oakland.

The project scope includes:

  • demolition of the existing building (with the hard and soft scapes)
  • development of a new 22,000 accessible two-story recreation and resilience center.

The new facility will include:

  • multipurpose classrooms
  • multipurpose room with stage
  • restroom facilities
  • central kitchen
  • interior & exterior community gathering spaces
  • indoor gymnasium facilities
  • roof garden
  • solar panels with battery backups

     


Additional Information

Lincoln Recreation Center project is located in Oakland's District 2. 

The broader project team includes Oakland Public Works (OPW), Oakland Parks, Recreation and Youth Development (OPYRD), the City’s Sustainability and Resilience Division, Friends of Lincoln Square, and the Asian Pacific Environmental Network (APEN). Shah Kawasaki Architects, an Oakland‑based Small Local Business Enterprise, serves as the project’s design firm.

During the construction phase, OPYRD continues to oversee park programming and daily operations, while Friends of Lincoln Square and APEN lead community organizing. OPW manages the project’s financial oversight and ensures functional project delivery. 

The project will be completed in two major phases. Phase 1 demolition is scheduled to begin in November 2026, followed by the first round of new construction. Phase 2 demolition will take place in Fall 2027, with the next construction phase beginning right after that work is complete.

Background

Built in the late 1970s as a 7,500‑square‑foot facility, the Lincoln Square Recreation Center has served as an anchor for Oakland’s Chinatown. It was the only public recreation center and park in Chinatown and Downtown Oakland with park staff, public restrooms, and active programming on-site. The Lincoln Recreation Center hosted programs and classes year-round serving patrons from preschoolers to seniors, including a thriving summer camp program. The facility received only minor capital improvements since its inception. As the most-used recreation center in the City and with the construction of multiple high-rise residential buildings in Chinatown and Downtown Oakland, the center required significant expansion to meet growing community demand. 

In the early 2010s, Friends of Lincoln Square, APEN, and the Rec Center’s Director began organizing conversations about the center’s future.

In the FY 2019–2020 Capital Improvement Program (CIP) budget cycle, OPRYD ranked the Lincoln Square Recreation Center as its #1 priority project for initial funding, securing seed funding and launching OPW's planning phase. 

 The project supports multiple City goals and strategies, including:

  • Oakland Strategic Plan(PDF, 47MB) (2025-2028): Aligning the budget with Citywide priorities by delivering on the City's Measure KK and U bond commitments for public safety infrastructure investment in Chinatown, and supporting cross-department collaboration and coordination between OPW and OPRYD.

  • Oakland 2045 General Plan(PDF, 6MB) – Safety Element:  Protecting residents, workers, and visitors from seismic and geologic hazards, fire hazards, hazardous materials, flooding, and other potential hazards that risk life and property.

  • Local Hazard Mitigation Plan(PDF, 25MB) : Replacing a non-code compliant recreation center with a modern recreation and resilience hub designed to current seismic and building code standards ensuring continued emergency operations following a major earthquake or other natural hazard event.

  • 2030 Equitable Climate Action Plan(PDF, 60MB) : Replacing a gas-dependent City facility with a new all-electric essential services building targeting LEED Gold certification.

This project vision's reflects community priorities that have expanded benefits for all Oakland residents.

Funding

The City allocated $1.7 million in FY20 to launch community engagement and early planning. It partnered with Friends of Lincoln Square and APEN to pursue major state grant opportunities, securing an $8.5 million Proposition 68 grant and a $9.25 million California Department of Food and Agriculture Community Resiliency Center (CDFA) grant in 2021 and 2022. Their shared efforts positioned the project to receive additional federal funding from the U.S. Department of Housing and Urban Development (HUD) and local funding from Measure KK and Measure U. Together, these combined sources positioned the project to move into design and construction.

Lincoln Sq Rec Ctr Funding logos.png

 

Resilience Center

A resiliency center reflects the community's needs during everyday activities and can be programmed for disaster planning. The Lincoln Recreation Center can provide shelter and essential services. The new facility will include solar panels and a battery back-up system. The new air‑conditioning system will deliver clean, cool air during wildfire season. The center will also have refrigerators for medicine, charging stations for cell phones, hookups for washers and dryers, and a second-floor roof garden for outdoor activities and relaxation. 

               

 

2024 0425_cd_img_cmp_elev_south_with SKA Logo.png

10th St. Aerial_with SKA Logo.png

Location

250 10th Street, Oakland, CA 94607  View Map

Google Map