Published on September 30, 2026
Major noise and demolition activities are planned from October 7, 2026, to November 20, 2026, within the construction zone shown above.
Heavy demolition will occur within the red boundaries located in the screenshot, between the hours of 8:00 a.m. to 4:00 p.m., Monday through Friday.
Falling debris and loud noise are expected.
Dust and airborne particles may be present.
Dust Control measures: Water down demolition materials and a temporary dust screen will be installed.
No unauthorized entry beyond posted barriers.
Only trained and approved personnel may enter the demolition area.
Caution: Watch for vehicles entering and exiting the site.
For park operation questions/concerns/comments, please contact Quincy Williams at qwilliams@oaklandca.gov or 510-424-3371. For construction project questions/concerns, please contact Mersedeh Haghighi Javid at MHaghighiJavid@oaklandca.gov or 510-238-2950.
Lincoln Square Recreation Center Project Page