Submit Revisions to Your Permitted Project

Revision Permit Icon

During construction, projects may encounter a need to revise their approved project plans. In most cases, the building inspector will identify the need for revisions and issue a correction notice with the steps that the project will need to undertake.

Below are the different types of revisions and processes to submit revised plans for review and approval by Oakland's Planning & Building Department. Please note that Zoning Worksheet (ZW) records are not permits; they are temporary application numbers assigned by the permitting system in order to route applications accordingly.

What's new: You can now request a revision to most issued building permits directly from your permit in the Online Permit Center. Open your permit and click Create Amendment. You no longer need a Building Worksheet or the Request for Permit Revision Form for building revisions. See the step-by-step guide (PDF)(PDF, 2MB)

Before you Start

Please review the Permit Requirements below as these vary from project to project.

Ready to get started?  First, make sure you are registered and activated at our Online Permit Center. For instructions, please visit our Planning & Building Video Tutorials webpage.

For a building revision, have these ready:

  • Your permit number (for example, B2501145).
  • The Online Permit Center account connected to the permit.
  • A short, specific description of what is changing.
  • The value of the revised work (materials and labor).
  • Updated plans saved as PDF files (no photos of documents; 300 MB total).
  • If an inspector gave you a correction notice, the inspector's name.

Permit Requirements

Who Can Revise Your Permits?

1.  Contractors who are licensed by the State of California with a classification appropriate for the work that will be performed and have a current Business Tax Certificate.

2.  Owners of a building or their legal representative.

 

 

Which permits can be revised online?

You can request a revision online when your permit is one of these types and its status is Permit Issued, Issued, or Reinstated:

  • Building Alteration and Residential Building Alteration
  • Building Residential Combo (RBC) Alteration
  • Building New and RBC New Construction
  • Electrical, Mechanical, and Plumbing (including 1 & 2 Unit Residential)
  • Sign Permit and Non-Residential Sign Alteration
  • Private Infrastructure
  • Solar Permit Commercial and Non-SolarAPP+ Residential Solar Permits
  • Grading

If you do not see the Create Amendment button on your permit, your permit type or status may not qualify. Please contact us and we will help you find the right path.

 

 

Select Revision Type

Building and Planning Revisions

If your project has made changes to the structure that are not part of the approved plan set issued by the City of Oakland, please follow the process below:

Step 1.Step One: Sign in and open your permit

Sign in to the Online Permit Center. Go to My Records and click your permit number.

Step 2.Step Two: Click Create Amendment

  • At the bottom of your permit page, click Create Amendment. This starts a Building Revision linked to your permit.

    Don't see the button? See "Which permits can be revised online?" above.

     

Step 3.Step Three: Complete the Online Revision form

  • Choose the applicant and check the owner information.
  • Confirm the parent permit number.
  • Describe the revision and answer a few questions (for example, whether it is due to an inspector's correction notice, and whether you are adding square footage or submitting plans).
  • Electrical, mechanical, and plumbing permits: list each type of work and quantity.
  • Enter the job value (materials and labor).

Upload your revised plans as PDF files. For plans, choose the document type BLD-Electronic Plans Submittal.

Step 4.Step Four: Pay and Submit

Review your answers, pay any fees, and submit. Your revision gets its own number: your permit number plus -R and a two-digit count (for example, B2501145-R01).

Step 5.Step Five: Revision Review

The City of Oakland Planning & Building Department will review your revision and email you directly if corrections are needed. Reply to the Plan Checker with your corrected plans.

*Electrical, mechanical, and plumbing revisions that do not need plans are approved right after you submit and pay.*

Step 6.Step Six: Approval

Once approved, the revision is added to your original permit. Keep the approved revision documents on site with your permit and approved plans, and keep scheduling inspections under your original permit number.

 

Step-by-step guide with screenshots (PDF)(PDF, 2MB)

 

 

Planning/Zoning Only Revisions

If your project has made changes to the exterior design of the building other than those originally approved by Planning/Zoning, please follow the process below:

Step 1.Step One: Zoning Worksheet

Apply for and submit a Zoning Worksheet (ZW) through our Online Permit Center*

* Note: You will be taken to our login/registration page before you can submit a Zoning Worksheet.

In the online ZW application:

  • Write "Planning/Zoning Revision" in the description of work field.
  • Upload your updated plans in the Documents section.

Step 2.Step Two: Application Review

A Planning/Zoning staff member will contact you by email.

Solar Plan Revisions (Minor) including SolarApp+

Minor Changes

If your solar project has minor changes (e.g., moving panels, changing the number of panels, or making changes to the electrical system), follow these steps:

Step 1.Step One: Online Revisions

  • Do not submit revisions via the online permit portal.

Step 2.Step Two: Field Inspection

  • Schedule a Field Inspection and have the proposed revisions on-site for the inspector to review. 
  • For SolarApp+ projects, please have the updated SolarApp+ approved plans and checklist. 
  • The inspector will update the permit description and upload the revisions to the system.

Step 3.Step Three: Review

For Electrical Changes (e.g., new main service panel/ upgrade, or Batteries (ESS))

Apply for same-day issuance for Electrical Permits by following the appropriate Residential or Commercial Project link(s) via our Mechanical, Electrical, and Plumbing (MEP) Permits webpage.

Solar Plan Revisions (Major) including SolarApp+

Major Changes

If your solar project has major changes, follow the process below based on the type of revision:

For Structural Changes

Step 1.Step One: Request a revision from your permit

Sign in to the Online Permit Center, open your solar permit from My Records, and click Create Amendment.

If an inspector referred you to a Plan Checker, answer Yes to the correction notice question and choose the inspector's name.

Step 2.Step Two: Complete, Pay, and submit

  • Describe the changes, upload your updated plans as PDF files, pay any fees, and submit. A Plan Checker will email you if corrections are needed. See the Building Revisions tab for details.

     

For Electrical Changes (e.g., new main service panel/ upgrade, or Batteries (ESS))

Apply for same-day issuance of Electrical Permits by following the appropriate Residential or Commercial Project link(s) via our Mechanical, Electrical, and Plumbing (MEP) Permits webpage.

Need to Know

Revision or Resubmittal

  • Revision: your permit is already issued and you want to change the approved work or plans. Use Create Amendment.
  • Resubmittal: your application is still in plan review and you are answering plan check comments. Upload your corrections to your existing application. Do not start a revision.
  • New permit: the new work is a separate project (for example, an addition on a different part of the property).

 

After your revision is approved

  • Your revision is linked to your original permit and a note is added to it.
  • Keep the approved revision documents on the job site with your permit and approved plans.
  • Schedule inspections under your original permit number, not the revision number.
  • A revision request stays open for 180 days. If it is not completed by then, it may expire.

 

Questions?

Please email us at bbpermit@oaklandca.gov or find quick answers through our Permit & Services Questions Portal. You may also schedule an appointment with Permit Counter staff during open hours.