This project will install Rapid Rectangular Flashing Beacons (RRFBs) and Intersection Lighting at six intersections in the City of Oakland with a history of pedestrian collisions.
This project is currently under construction.
Shattuck Avenue & 56th Street Project Update as of October 2026:
Repaving for the Shattuck Avenue and 56th Street intersection is underway. Please see below for our approximate construction schedule:
At this time, we are working to maintain thru-traffic for both Shattuck and 56th during construction- however, please note that unforeseen underground conditions may require traffic on 56th to be shutdown at night (traffic on Shattuck would be maintained).
New intersection lighting (not shown)
Formalized diagonal diverter
Pole-mounted RRFB at raised crosswalk at eastern leg
6’ wide median island at east crosswalk
Double curb ramps at all corners
Stripe 3 new continental crosswalks
Project Update as of October 2026 Remaining work includes landscaping installation, electrical work, and final signage and striping. Plant species have been approved, and the contractor is awaiting procurement of materials before landscaping installation can proceed. The City will provide updated schedule information as it becomes available.
Project Update as of October 2026 Remaining work at this intersection includes electrical work and final signage and striping. The City is coordinating with the contractor to obtain an updated schedule and will share additional information as it becomes available.
Project Update as of October 2026
Remaining work includes electrical work and final signage and striping. The City is working with the contractor to confirm the schedule for the remaining items and will provide updates when available.
Project Update as of October 2026 Remaining work at this intersection includes electrical work and final signage and striping. The City is coordinating with the contractor on the schedule for completing the remaining items and will share updated information as it becomes available.
Project Update as of October 2026 Raised Concrete Crosswalk and additional Sewer department work at this intersection has been completed. Remaining work includes electrical work and final signage and striping. The City is coordinating with the contractor on the schedule for this work and will share updated information as it becomes available.
Project Update as of October 2026:
This project will install side street signal mast arms, Leading Pedestrian Iintervals (LPIs), Rapid Rectangular Flashing Beacons (RRFBs), pedestrian refuge islands, and left-turn-only signal phases at pedestrian collision locations on 98th Avenue between Pearmain St and Birch St.
This project is expected to begin construction in Spring of 2027.
This project will install a combination of Rapid Rectangular Flashing Beacons (RRFBs), left-turn-only signal phases, pedestrian countdown heads, and Leading Pedestrian Intervals (LPIs), at locations with a history of pedestrian collisions, as well as a road diet between Mandela Parkway and Brush Street on 14th Street.
This project is expected to begin construction in Fall 2026.