Mosswood Community Center

This Summer Oakland will launch an effort to design and build a new Community Center at Mosswood Park. The community will be an essential partner in this effort, beginning with a Visioning and Master Plan Phase. Together we will envision the possibilities for the future Community Center and Park. It is critical to the success of this facility that we hear from YOU.

Timeline

Project Launch
June 2019
Visioning + Master Plan Phase
July - December 2019
Community Center Design + Fundraising
January - June 2020
*Design Drawings (*pending funding availability)
July 2020 - March 2021
Bid + Award
April - September 2021
Construction
October 2021 - April 2023

About

In November 2016, the Mosswood Recreation Center, built in 1953, burned to the ground. Temporary facilities have been installed to house core center programs, such as after school programs, summer camp, computer lab and cooking classes, until the new Center is built.

The vision for the new Community Center is to create a vibrant destination for civic, cultural, social, educational, and recreational activities. The Community Center will incorporate sustainable design principles and the City's ‘Art in Public Places’ program. It will be inclusive of a diverse community of users, universally accessible, flexible in use, and thoughtfully designed.

Mosswood Park is an iconic Oakland institution and North Oakland cultural hub. The eleven-acre public park was established in 1910, and is operated by the Oakland Parks, Recreation and Youth Development Department. The park has been the home of pre-famous NBA players and decades of significant cultural events. The Community Center project will be planned and developed through an intensive community engagement process, and the design team and City staff will engage with community stakeholders throughout the design process. The purpose of the initial Visioning, Programming, Park Master Plan and Concept Design Phase will be to explore -with the community- the feasibility of options for the Community Center, while preserving and enhancing the overall park experience. The City currently has funding for Design, but additional funds must be raised in order to build the new Community Center.

For questions about the project, please contact Project Manager, Christine Reed.

Contact Us

Map location for Mosswood Community Center, located at  in ,

,

Phone Numbers

Email Address

Creed2@oaklandca.gov