High Street Pedestrian Safety Improvements

The High Street Project installs pedestrian safety improvements on High Street, a high injury corridor, between San Leandro Street and 580.

Status:
In Process
Start date:
Jan 1, 2014

About

A summary of project features include the following on High Street:

  • Installation of new ADA curb ramps and pedestrian countdown heads at San Leandro Street, Bond Street, and Bancroft Avenue.
  • Installation of new signal mast arm poles and pedestrian countdown heads at Brookdale Avenue.
  • Installation of a variety of crossing improvements including: four (4) rectangular rapid flashing beacons, a pedestrian hybrid beacon, high visibility striping and advanced limit lines.

Map

Map of Project: High Street Pedestrian Safety Improvements

Timeline

Construction
Summer 2021-Spring 2022