2021 Oakland Hills Paving Project

This project addresses the majority of local streets mileage in the Oakland Hills prioritized in the 2019 3-Year Paving Plan.

Status:
Planned
Start date:
Jun 14, 2021

About

This project will complete pavement rehabilitation on the following streets in 2021. The following schedule is subject to change.

Construction will start the week of:

  • 6/14/21
    • ALVARADO RD (from CLAREMONT AV to AMITO AV)
    • ALVARADO RD (from CITY LIMIT to CITY LIMIT)
    • CLAREMONT AV (from ALVARADO RD to GRIZZLY PEAK BV)
  • 6/21/21
    • GRAND VIEW DR (from HILLER DR to DOROTHY PL)
  • 6/28/21
    • OSTRANDER RD (from BROADWAY TERR to ROMANY RD)
  • 7/12/21
    • DULWICH RD (from HARBORD DR to HERMOSA AV)
    • FLORENCE AV (from HARBORD DR to EAST END)
    • FLORENCE AV (from HERMOSA AV to BROADWAY TERR)
    • HERMOSA AV (from FLORENCE AV to BROADWAY TERR)
    • JACOBUS AV (from HERMOSA AV to EAST END)
    • MORPETH ST (from FLORENCE AV to HARBORD DR)
    • SHERIDAN RD (from BROADWAY TERR to SOUTH END)
  • 7/26/21
    • SAINT PAUL CT (from PROCTOR AV to MASONIC AV)
    • TRUITT LN (from CLAREWOOD DR to NORTH END)
  • 8/2/21
    • GREENVIEW DR (from ROYAL OAK RD to ROYAL OAK RD)
    • LANE CT (from NORTH END to HARBORD DR)
    • MARR AV (from HARBORD DR to LANE CT)
    • SEQUOYAH VIEW CT (from SEQU. VIEW DR to SOUTH END)
    • SEQUOYAH VIEW DR (from OAK HILL RD to OAK HILL RD)
  • 8/9/21
    • THORNHILL DR (from SOBRANTE RD to SNAKE RD)
  • 8/16/21
    • FONTAINE ST (from GOLF LINKS RD to FONTAINE OVRPSS)
    • HOLMES AV (from FONTAINE ST to GREENLY DR)
  • 8/23/21
    • LEONA ST (from MOUNTAIN VIEW to RUSTING AV)
    • MOUNTAIN BLVD (from KUHLNE AV to CALAVERAS AV)
    • MOUNTAIN BLVD (from MONZAL AV to NORTH END)
  • 8/30/21
    • BALMORAL DR (from SKYLINE BLVD to NORTH END)
  • 9/6/21
    • ASCOT DR (from MOUNTAIN BLVD to CHELTON DR)
    • BAGSHOTTE DR (from WESTOVER DR to CHELTON DR)
    • CASTLE PARK WY (from CASTLE DR to CASTLE DR)
    • CHELSEA DR (from CHELTON DR to GIRVIN DR)
    • CHELTON DR (from HAVERHILL DR to CHELSEA DR)
    • JOAQUIN MILLER (from MOUNTAIN BLVD to SOUTH END)
    • LA CUESTA ST (from CAMINO LENADA to ASCOT DR)
  • 9/13/21
    • LA SALLE AV (from MOUNTAIN BLVD to MORAGA AV)
    • SNAKE RD (from MOUNTAIN BLVD to COLTON DR)
    • ZINN DR (from DRAKE DR to NORTH END)
  • 9/27/21
    • ABBOTT DR (from SHERWOOD DR to EAST END)
    • ALHAMBRA LN (from THORNHILL DR to SOUTH END)
    • CROWN AV (from MERRIEWOOD AV to MERRIEWOOD AV)
    • MARDEN LN (from MERRIEWOOD DR to SOUTH END)
    • MERCED AV (from MORAGA AV to LUCAS AV)
    • MERRIEWOOD DR (from TAURUS AV to SHERWOOD DR)
    • ROBIN HOOD WY (from MERRIEWOOD DR to EAST END)
    • TAURUS AV (from MERRIEWOOD DR to VALLEY VIEW RD)
  • TBD
    • BIEHS CT (from HARBORD DR to EAST END)
    • SHELTERWOOD DR (from SHEP.CANY.RD to WESTOVER DR)
    • THACKERAY DR (from WESTOVER DR t0 CHELSEA DR)

Timeline

Tree Trimming in Advance of Paving
March - May 2021
Paving
June 2021 - August 2021 (Anticipated)